BagsAndYards

Concrete for a 8×10 slab

A 8×10 ft slab at 4″ thick needs about 49 × 80 lb bags of concrete mix (with 10% waste) — or 1.25 cubic yards of ready-mix. Estimated materials cost ≈ $319 (bags). This is a bag-and-mixer pour: the excavation and the base take longer than the concrete.

Area80 sq ft
Volume26.67 ft³ = 0.99 cu yd
80 lb bags (no waste)45
80 lb bags (10% waste)49
60 lb bags (10% waste)66
Ready-mix1.25 cu yd
Finished slab weight≈ 3,733 lb
RecommendedBuy bags

What a 8×10 slab is usually for

  • 8×10 prefab shed
  • Hot tub pad
  • Firewood store
  • Small workshop annex

8×10 is the single most common prefab shed footprint in North America, which is why kit instructions so often assume it. If the shed is going on top, check the manufacturer's drawing before you set forms: some kits want the slab exactly at the shed footprint so the wall sheathing sheds water past the edge, others want a 2–3 inch reveal all round to keep the bottom plate off wet concrete.

Adjust it

Change the size, thickness, bag size, or waste % below:

How much concrete do I need?

ft
ft
in
%
You'll need about
Bags (with overage)
Bags (no overage)
Ready-mix (delivered)
Estimated materials cost

Estimate for standard concrete mix (e.g. Quikrete #1101 / Sakrete High-Strength). Bag counts round up and include your overage %. Cost is an estimate (as of June 2026, US national average) — confirm bag price and ready-mix delivery (often a 1 yd³ minimum + short-load fees) with your supplier. Not a substitute for a structural engineer on load-bearing work.

📘 Sequence for a pad this size: how to form and pour a small slab

Mixing a 8×10 pad before it sets

Wheelbarrow loads≈ 9 (at 3 ft³ each — weight-limited, not volume-limited)
Mixer batches≈ 25 at 2 bags per batch
Rough mixing time≈ 2.1 hours of continuous mixing, one person
Finished weight≈ 3,733 lb on the ground

That is a realistic one-day job for one determined person with a rented mixer, or a comfortable morning for two. Mix continuously and keep placing into the edge of what you have already poured so each batch knits into the last before it starts to stiffen. The order of operations is form, base, mix, finish, cure.

Budget for the tools as well as the concrete: a mixer runs about $70/day, a plate compactor for the base about $80/day, and a concrete saw for the joints about $60/day.

Why bags win on a 8×10 pad

At 0.99 cubic yards, this slab sits just below the point where a truck usually makes sense. Here is the comparison with the fees included:

RouteWhat you orderEstimated cost
Bags (80 lb)49 bags at ≈ $6.50 each≈ $319
Ready-mix delivered1.25 yd³ at ≈ $165/yd³ , plus a short-load fee≈ $256–$356

Ready-mix is the better call at this size, even carrying the short-load fee. Beyond the price, a truck delivers the whole slab as one continuous placement — no cold joints between batches, no risk of the first section setting while you mix the last, and a consistent mix throughout. Mixing 49 bags to match it is a full day of heavy work with a worse result.

The short-load fee is what people miss. Suppliers charge it below roughly 4 cubic yards, typically $50–$150, because sending a truck out costs them the same whether it is full or not. Always ask for the delivered total including fees rather than the per-yard rate. The full reasoning is in bags vs ready-mix concrete.

Thickness on a 8×10 pad

Thickness is the one input that changes the order most, and it is chosen by what will sit on the slab rather than by budget. Here is the same 80 sq ft footprint at each common depth:

Thickness80 lb bagsReady-mixEst. materialsTypical use
3.5″431 yd³≈ $280What a nominal 4″ pour often actually measures
4″ (this page)491.25 yd³≈ $319Patios, sheds, walkways, foot traffic
5″621.5 yd³≈ $248Cars, light trailers, frequent vehicle use
6″741.75 yd³≈ $289Trucks, RVs, machinery, heavy loads

Going from 4″ to 6″ on this slab adds roughly $0 in materials — about 0% more. That is the entire cost of the decision, and it is why the advice for anything carrying a vehicle is to just pour the extra inches. Removing and replacing a cracked slab costs many times the difference.

The 3.5″ row is not a recommendation, it is a reality check: a “4 inch” slab poured on a subgrade that is a little high in places genuinely finishes at 3.5″ in those spots. If your base is not dead flat, order to the thicker figure. More on this in concrete slab thickness: 4″ vs 6″.

Control joints on a 8×10 pad

Concrete shrinks as it cures and it will crack — the only question is whether it cracks where you decided or where it chose. Control joints are the decision. The rule of thumb is a maximum spacing in feet of about two to three times the slab thickness in inches, so at 4″ that is 8–12 ft.

At 8×10 this slab fits inside a single panel at the maximum allowed spacing, so the rule does not force any joints on you. That said, a hard-freeze climate or a subgrade you are not confident about is a good reason to cut one anyway — a tooled joint disappears within a season, whereas a random shrinkage crack is permanent. The sequence is in forming and pouring a small slab.

Does a 8×10 pad need mesh?

Reinforcement does not stop concrete cracking; it holds the crack tight so the slab keeps acting as one piece. For a residential slab-on-grade of 80 sq ft, either of these is conventional:

OptionTakeoff for 8×10
Welded wire mesh (6×6)2 sheets of 5 × 10 ft, allowing a 6″ lap all round
Rebar grid at 16″ o.c.9 + 7 bars = 142 linear ft ≈ 8 × 20 ft sticks
Tie wire≈ 63 intersections to tie

Whichever you use, it has to sit in the middle of the slab to do anything. Mesh laid on the ground and walked over during the pour is the most common wasted material on a DIY slab — it ends up at the bottom, where it carries no tension at all. Use chairs or bar supports, and lift as you go if you have no other option.

Watch out on a pad this size

Hot tubs are the trap at this size. A filled tub with bathers runs well over 100 lb per square foot, far more than a shed, and most spa manufacturers ask for a thicker reinforced pad than the 4 inch default here. Read the spa's siting sheet before you order the concrete.

The arithmetic

Volume = 8 × 10 × (4 ÷ 12) = 26.67 ft³, then ÷ 27 = 0.99 cubic yards. An 80 lb bag yields 0.60 ft³, so 26.67 ÷ 0.60 = 45 bags before waste; add 10% and round up to 49 bags. Ready-mix rounds up to the quarter yard, giving 1.25 yd³. Every constant behind those steps is documented in how we calculate, and the reasoning is in how much concrete do I need?

Other slab sizes

See all slab sizes →

Last updated: 2026-08-21.
Bag yields from the QUIKRETE #1101 data sheet. Joint spacing, panel aspect and cut depth follow standard residential practice (2–3 × slab thickness, 1.5:1 max panel ratio, cut to ¼ depth). Cost figures are US-national-average estimates and vary by region and supplier. Planning estimates only — see terms.